Carver manufacturers with you to understand the installation of carver machine need to pay attention to matters
Carving machine installation needs to pay attention to what are the following with small series to understand:
Must put the balance after 1, machine tool is in place, can use shim adjustment, ensure machine work surface horizontal ー - adjust the level of machine tool
2 (1) machine tool connection, one by one according to the electrical wiring diagram and piping diagram connection. Connect to pay special attention to ensure that clean, tubing, water pipe connection, to
Prevent foreign matter from entering the pipeline from the interface, and tighten every joint to keep the seal. Cable connection to ensure reliable plug, plug, be sure to tighten the strong screw, ensure reliable contact. After cables and pipelines are connected, all pipelines should be fixed in place.
2 (2), the grounding end of the electric control cabinet must be grounded, or connected to the spindle cooling system as required.
3, power test machine, power before: to determine the current control system requirements of the power supply and power supply consistent, and in the motorized spindle cooling machine coolant box and cut
Fill the cutting fluid tank with specified cooling fluid and cutting fluid.
4. Switch X, Y and Z axes. Manually check whether the work is normal and whether the optical check and travel switch are working. Manually continuously move each axis, accurately correct the origin, check whether the accuracy of the origin of the machine tool is within the allowable error range. Check the working conditions of auxiliary functions and accessories, such as: whether the machine lighting is normal; After filling cutting fluid as required, test whether universal tubing can eject cutting fluid normally and whether cutting fluid leaks out; Rotation of the coordinate axis is normal; Whether the tool setting instrument works normally.